The Ladysmith Wal-Mart project started in the middle of April 2007. All of the dirt and gravel was placed by the middle of June 2007. This leaves only topsoiling behind the back of curb and a few other small items.
Some of the quantities include: 60,000 yards of common excavation, 11,000 yards of topsoil, 51,000 yards of EBS, and 45,000 ton of breaker rock and gravel. The job is on schedule, and going very well. The EBS quantity is a lot higher then expected, but they still were able to stay on schedule.
Some of the guys that have had a big part in the project our as follows: Shawn Hoffman, Chris Demers, Tom Freagon, Mike Windsor, Dale Gower, Jerry Harms, Bob Briggs, Ray Laufenberg, Ryan Stubrud, Clint Johnson, and Dan Stewart. Oh by the way, I think everyone should experience at least one Wal-Mart site. Lol!
|